October 15, 2026
The sand at Midtown Beach is new this year. Starting in March 2026, more than 500,000 cubic yards of offshore sand was dredged and spread across 3.4 miles of shoreline from Seminole Avenue to Banyan Road. Weather pushed the finish date to May 16.
That renourished beach may be open for only a few more weeks. Palm Beach town staff expect to start building a new Midtown seawall in December, and the work is scheduled to take 18 months. During roughly the same weeks, Phipps Ocean Park on the South End is expected to reopen after a redevelopment that closed it in May 2025. So for about a year and a half, the island's everyday lifeguarded beach will be at the south end of the island. The open questions about how that works are on the town's agenda this month.
The timing was planned. Town Engineer Patricia Strayer told the Palm Beach Civic Association in May that the sand in front of a seawall is its first line of defense against the surf. She said she pushed to get the Midtown renourishment done before the new wall goes in.
The current wall dates to the 1920s. It is sheet pile with a concrete cap and runs 2,715 feet from Royal Palm Way south to Gulfstream Road. Town officials say failure is not imminent. Jake Hurley, senior project engineer with the Public Works Department, told the Town Council that multiple engineering reports place the wall "near the end of its useful life." He also said replacing it ahead of time costs much less, and disrupts much less, than an emergency repair.
According to Palm Beach County Property Appraiser Dorothy Jacks, the wall protects $7 billion in private property. It also protects public streets and utility and telecommunication infrastructure. One of those streets is South Ocean Boulevard. The replacement is expected to cost $20 million or more. That figure includes the $1.5 million the council set aside in July for design and planning.
From the beach, the new wall will look much like the current one. The structural wall's elevation stays at roughly 15.9 feet. Plans call for removing and replacing the knee walls, gates, beach access stairs and ramps along Midtown. Those stairs and ramps are how people get onto the sand, which is why the closure question is still open.
At the September 8 council meeting, staff said the town plans to close Midtown Beach "either partially or entirely" for the length of construction. A full closure would keep the public off Midtown from December until spring 2028. Midtown is one of only two public beaches in town with lifeguards.
Hurley explained that the plan from the design-builder, Murray Logan Construction of West Palm Beach, includes building a dune that leaves little room for beach access. Staff will ask the contractor what keeping part of the beach open would involve. Hurley expects it would "very likely" add time and cost to the project.
Some of the details are already set. South Ocean Boulevard will keep two-way traffic throughout the work. In May, Strayer told the Shore Protection Board there would be no parking at Midtown Beach during construction, and that the nearby Clarke Avenue beach would stay open. Hurley expects traffic to improve for the length of the project, because "we're not going to have individuals coming from off-island to park at the beach."
The schedule has already moved once. In May and again in August, the start was described as early 2027. By September it had moved up to December. Several decisions are coming in quick succession:
| Date | What's scheduled | Status as of October 8, 2026 |
|---|---|---|
| October 28 | Architectural Commission review of the Midtown Beach Linear Park redesign | Scheduled |
| October 29 | Town outreach meeting on construction impacts, beach closure and traffic | Planned, flier to circulate beforehand |
| As early as November | Murray Logan's guaranteed maximum price, drawings and detailed schedule | Expected |
| November | Phipps Ocean Park reopens | Latest stated window, no exact day |
| December | Seawall construction begins | Current estimate |
| Spring 2028 | Midtown Beach reopens after seawall work | Projected |
At the October 29 meeting, the town plans to cover what construction means for residents, including the Midtown closure and traffic. Murray Logan's guaranteed maximum price, which is the all-inclusive cost to finish the wall, will come with drawings and a much more detailed schedule. That package is likely the first document to show what partial access would actually look like.
Council member Lew Crampton, a South End resident, raised the obvious follow-up at the September meeting:
"Those folks are going to go south, and you are going to have a potential overload there."
He named the beaches east of Sunrise Avenue and Phipps Ocean Park as the likely places displaced beachgoers would go. He also said the council should talk more before deciding between a partial and a complete closure.
Phipps is getting that job at the same moment it reopens. The town owns the park. The Preservation Foundation of Palm Beach is leading the redevelopment in cooperation with the town. The contract carries a $31 million guaranteed maximum price. That includes $29.7 million for the park itself, $674,000 to renovate the lifeguard station and $392,000 for the tennis courts. The tennis center and its parking reopened on November 1, 2025. The rest of the park has stayed closed, with November 2026 as the reopening window.
The Foundation describes the park as a public beach and park running from the Atlantic to the Intracoastal, with 1,200 feet of oceanfront. When construction started in 2025, the plans included:
That list comes from the 2025 plan. Since then, Strayer told the council in April that construction was on schedule but that design changes had made the completion date less certain. At that point, the town was still aiming for September. The reopening has moved once, and an exact day has not been announced.
The redesign also changes what kind of park this is. Much of the Phipps program is about teaching, restoration and walking: the classroom, the nursery, the schoolhouse and the paths. For the next 18 months or so, the same park will also be the island's main lifeguarded beach for anyone who used to walk or drive to Midtown.
When the wall is finished, the strip behind it is set to change too. The town has budgeted about $4 million to redo the Midtown Beach Linear Park, with work timed toward the end of seawall construction. The Palm Beach Daily News reported a tentative park construction start of summer 2028. The design team includes landscape architect Sean Twomey of Environment Design Group and the architecture firm Bridges Marsh & Associates.
The concept before the Architectural Commission on October 28 includes:
The 42 coconut palms in the park are part of the review. Strayer said the town wants to keep as many as it can. Palms will stay where they are when possible or be moved and replanted in the park, though some will likely need to be replaced. The August concept also removed six parking spaces along South Ocean Boulevard.
The Midtown changes reach the west side of the island as well. The Society of the Four Arts is renovating and expanding its Midtown campus. The Lake Trail segment through the west side of that campus is closed because it runs through the construction site. The Four Arts renovation FAQ says signs direct trail users back to the route. It does not give a reopening date.
So by December, both waterfront walking routes at Midtown may be partly fenced off: the Lake Trail at the Four Arts and the oceanfront walk along the seawall. Until then, Midtown is open on renourished sand, and the October 28 and October 29 meetings are when the town will take up how much of it stays open after that.
Changes to a public beach can matter to anyone who owns or rents along South Ocean Boulevard, and to the condo owners and landlords whose buildings sit behind the wall. If you'd like a clear read on what the Midtown construction schedule means for a home you own on the island, Power Duo Group can walk through it with you. You can start with your Instant Home Valuation.